Free calculator · Prioritization

WSJF Calculator

Rate every job for business value, time criticality, risk reduction and size, and get its Cost of Delay, its WSJF score and the ranking. Free, with no sign-up, and your list never leaves your browser.

Your jobs

Calculator
Scale

SAFe’s modified Fibonacci scale: 1, 2, 3, 5, 8, 13, 20.

  1. WSJF score 7.67 CoD 23
  2. WSJF score 12 CoD 12
  3. WSJF score 2 CoD 16
  4. WSJF score 4.4 CoD 22
  5. WSJF score 1.38 CoD 18
  6. WSJF score 1 CoD 5
Ranking · highest score first
  1. 1 Fix the checkout timeout 12
  2. 2 Update invoices for the new tax rule 7.67
  3. 3 Upgrade the payment library 4.4
  4. 4 Single sign-on for enterprise customers 2
  5. 5 Rewrite the reporting engine 1.38
  6. 6 Dark mode 1
What the ranking says

Fix the checkout timeout comes first, 57% ahead of Update invoices for the new tax rule.

  • Do the highest score first: for its size, it is the job that costs you the most while it waits.
  • The ratings are relative. In each column, the smallest job on the list gets a 1.
  • A big job with a low score isn’t unimportant. Split it and score the parts.

Your list stays in this browser tab. Nothing is sent or saved, so download the CSV to keep it.

Now score them with your team

One person can’t rate both the value and the size. Start a WSJF assessment in FreeAssess with the jobs on your list: everyone scores on their own device, and the ranking uses the team’s averages.

Only the names go along, inside the link. The app shows them and asks before it creates anything.

Start with these 6 jobs (opens in a new tab)

How to calculate WSJF

Weighted Shortest Job First ranks jobs by what a delay costs, divided by how long the job takes. It takes two steps: add up the Cost of Delay, then divide by the job size.

  1. List the jobs. Keep them at a similar level: features with features, not a bug fix next to a year-long program.
  2. Rate one column at a time. Find the job with the least business value and give it a 1. Rate every other job against it. Then do the same for time criticality and for risk reduction.
  3. Rate the job size the same way. The people who will do the work rate it, and the smallest job gets a 1.
  4. Add the first three ratings. That is the Cost of Delay.
  5. Divide by the job size, and work from the highest result down.

An example: invoices have to change for a new tax rule. The business value is moderate (5), the deadline is fixed (13), and missing it would mean fines (5). The Cost of Delay is 5 + 13 + 5 = 23. The job is small (3), so WSJF = 23 ÷ 3 = 7.67.

The calculator above shows both numbers for every job: the WSJF score, and the Cost of Delay (CoD) next to it.

The four ratings

Value
Business value. What the job is worth to users and to the business: revenue, savings, satisfaction.
Time
Time criticality. How fast that value fades. Is there a deadline, a season or a competitor about to move?
Risk
Risk reduction and opportunity enablement. What the job protects you from, or what it makes possible later.
Size
Job size. How long the job takes. Size stands in for duration: a small job frees the team sooner.

None of these is measured in money or days. Each one is a comparison with the other jobs on the list, which is why WSJF works in a planning meeting: nobody has to forecast revenue, they only have to agree that one job is about twice as urgent as another.

The scale: Fibonacci or 1 to 10

The calculator offers two scales. Switch with the Scale buttons above the list; ratings that don’t exist on the new scale move to the nearest value.

SAFe
Modified Fibonacci. 1, 2, 3, 5, 8, 13, 20. The gaps grow with the numbers, so nobody argues over a 6 against a 7, and a rating of 13 says clearly that this job is in another league.
1–10
Linear. Every whole number from 1 to 10. Familiar, and the scale the FreeAssess template uses.

Whichever you choose, use it for all four ratings. If business value ran from 1 to 20 and time criticality from 1 to 5, value would decide every score.

What the score means

A WSJF score has no unit. It says how much relief you get for a unit of work: a job that scores 6 is about three times as rewarding to do next as a job that scores 2. Only the ranking matters, and only within one list, because the ratings are relative to the other jobs on it.

Two jobs with the same Cost of Delay don’t get the same score. The smaller one goes first, because it delivers its value sooner and frees the team for the next job. That is the “shortest job first” in the name.

The ranking changes over time. As a deadline comes closer, time criticality goes up; once it has passed, it may drop to 1. Score the list again before each planning round.

What WSJF can’t tell you

  • Large jobs keep losing. Dividing by size means a big strategic job can sit at the bottom for a year. Split it into parts that deliver value on their own, and score those.
  • It doesn’t know about dependencies. If one job has to come before another, the formula won’t tell you.
  • Relative scores don’t travel. A 13 on one team’s list and a 13 on another’s are not the same thing. To compare across teams, score the jobs in one session.
  • Mixed sizes break the scale. When the list holds a two-hour fix and a six-month program, the scale has no room for what lies between them.
  • The ratings are still opinions. A confident voice can push time criticality to 20. Ratings made independently by several people hold up better.

If you have usage numbers and no deadlines, the RICE score calculator may fit better.

From your list to a team decision

WSJF needs two kinds of knowledge that rarely sit in one head: product owners and business people know the value and the urgency, and the people doing the work know the size.

FreeAssess runs that as a live session. The button under the calculator starts a WSJF assessment with your jobs already in it. Share its link: everyone scores from their own device, without an account, and the WSJF score uses the average of their answers. The template rates every metric from 1 to 10; you can change the scales in the designer.

New to the method? The WSJF guide explains where it comes from, when it fits and what to use instead.

More free calculators

All 4 calculators

Sequence your backlog together

Product rates the value, engineering rates the size. Put both in one WSJF assessment and let the formula settle the order.

We use cookies to improve your experience, analyze traffic, and serve personalized ads. Read more in our Cookie Policy.